System specifications
  • 1.92 MWh of energy delivered at a peak power of 500 kW
  • 12 x Energy Pods, each containing 16 x ZBM2 batteries
  • 4 x 125kW Dynapower MPS-125 EHV commercial inverter systems
  • Integration with thirdparty Siemens microgrid controller
  • Cloud based battery management system
Background

Anaergia is a global leader in the production of clean energy, fertilizer, and recycled water from virtually any waste stream. As part of their drive to deliver sustainable energy creation, Anaergia decided to install a flow battery storage solution in their new waste to energy Rialto Bioenergy Facility in California. The facility provides organic waste recycling and renewable energy generation services to local government authorities and solid waste haulers.

Anaergia constructed an on-site microgrid as part of the project to maximize the use of on-site generated power and to limit their peak load from the grid. The microgrid project was funded in part by a grant from the California Energy Commission and consists of batteries, a biogas conditioning system to support a 2MW biogas-fueled cogeneration unit, and a control system.

Redflow was selected as the supplier for the energy storage system due to their use of sustainable materials and the associated high energy density of the flow battery.

Solution

Redflow designed a 2 MWh energy storage system comprising of 192 zinc-bromine flow batteries to store energy and reduce peak energy use. To meet the facility’s requirements Redflow designed Energy Pods, each containing 16 Redflow batteries and the power electronics to link to external inverters. The Energy Pod enables Redflow to build scalable, megawatt hour sized storage systems more effectively. This energy storage system is the largest single sale and deployment of flow batteries globally.

The 12 Energy Pods are grouped into four banks of three pods with each bank connecting to the microgrid via a Dynapower 125 kW inverter. The inverters and energy storage system are integrated into a Siemens microgrid controller. This implementation demonstrates that the Redflow Energy Pods can work seamlessly with a range of other clean energy technologies to create sustainable energy systems.

Remote monitoring and control are provided by Redflow’s cloud-based battery management system. The battery management system manages the Energy Pods, the individual batteries in each pod, and the inverters. In parallel to the cloud facility, data can be retrieved from each battery using industry standard protocols.

Outcome

Our technical team successfully completed installation and commissioning of the 2 MWh energy storage system at the Rialto site in December 2021. The four battery banks have now been successfully charged and discharged and have passed critical acceptance testing criteria. The final test of the entire system will be executed in January 2022 when Siemens integrate the batteries into the microgrid controller, and the facility can draw on the entire 2 MWh of energy.

Click here to download Redflow's case study.

Anaergia-Installed-A5-300-2-W

“Anaergia selected Redflow’s zinc-bromine flow batteries because they are uniquely suited to meet the demands of the Rialto site.”

Yaniv Scherson

Chief Operating Officer

Redflow_RGB300

+ 61 7 3376 0008
[email protected]

Be the first to know

Sign up to our newsletter today.

This field is for validation purposes and should be left unchanged.

© Copyright Redflow Limited 2024. All rights reserved.

Keep in touch. Follow us and stay up to date.

   

Hey there, this is the default text for a new paragraph. Feel free to edit this paragraph by clicking on the yellow edit icon. After you are done just click on the yellow checkmark button on the top right. Have Fun!